Overview

Total capacity: 151.95 MW, divided into 03 phases:

  • – Phase 1: 39.95 MW (17 turbines, 2.35 MW)
  • – Phase 2: 64MW (16 tuabin, 4 MW)
  • – Phase 3: 48MW (12 tuabin, 4MW)

Trung Nam Wind Power Project was inaugurated on April 16, 2021

Mission of Trungnam SMC

Transport & install of Wind turbines using 3 x 800 tons crawler cranes, 3 x 180 tons crawler cranes, 1 x 220 tons mobile cranes, 6 130 tons mobile cranes.

Installation of wind turbine blades by crawler crane 800 tons

Scale

Address
Bac Phong Commune, Thuan Bac District, Ninh Thuan Province
Total capacity
151.97 MW
Number of wind towers
45 towers

Relevant experience

Super-long and super-heavy transportation
See details
Wind power No. 5 Ninh Thuan
See details
Trung Nam Thuan Nam solar power
See details
Dong Hai 1 – Tra Vinh wind power project
See details
Project of resolution on inundation caused by flood tide in Ho Chi Minh city considering climate change factor – Phase 1
See details