Ca Mau 1B Wind Power
![Trungnam SMC hoàn thành lắp đặt các trụ tuabin gió tại dự án điện gió Cà Mau 1B.](https://trungnamsmc.com.vn/wp-content/uploads/2022/11/THI-CONG-DG-CA-MAU-1B-01-1170x400.jpg)
Overview
Ca Mau wind power plant phase 1 has a total capacity of 350MW, including 4 wind power plants 1A, 1B, 1C and 1D with a total investment capital of more than 10,000 billion VND was invested by Trade and Construction Corporation (WTO).
In phase 1, the investor will install 83 wind turbines with a capacity of 4.5MW/turbine. The total power generation capacity of the project is expected to reach 1.1 million MWh/year. This is one of the key wind power projects of Ca Mau province.
![Trungnam SMC hoàn thành lắp đặt các trụ tuabin gió tại dự án điện gió Cà Mau 1B.](https://trungnamsmc.com.vn/wp-content/uploads/2022/11/THI-CONG-DG-CA-MAU-1B-01.jpg)
Ca Mau 1B Wind Power Project.
Trung Nam SMC's mission
Receiving high trust from the general contractors Powerchina and Huadian, Trungnam SMC participated as the main contractor to construct and install 7 wind turbine towers at Ca Mau 1B wind power plant with a capacity of 5.5MW/turbine.
Trungnam SMC used a 14,000MT installation barge system, equipped with 1,250MT crawler cranes, 250MT crawler cranes and 130MT crawler cranes to participate in the lifting and installation of the wind power equipment.
![Hệ thống sà lan lắp đặt của Trungnam SMC.](https://trungnamsmc.com.vn/wp-content/uploads/2022/11/THI-CONG-DG-CA-MAU-1B-02.jpg)
The 14,000MT installation barge system of Trungnam SMC.
![Trungnam SMC đã huy động toàn bộ nguồn nhân lực, chia ca thực hiện 24/24 để hoàn thành công việc.](https://trungnamsmc.com.vn/wp-content/uploads/2022/11/THI-CONG-DG-CA-MAU-1B-03.jpg)
Trungnam SMC has mobilized all engineer resources, divided shifts to perform 24/24 to complete the work.